The Millennium Challenge Account Nepal (MCA Nepal) has begun distributing compensation for land needed for the construction of electricity transmission line towers in the Tanahun district, part of a US-funded project.
The 400 kV transmission line will connect the Ratamate substation to the Damauli substation and then to the New Butwal substation. On September 17, the District Administration Office (DAO) Tanahun issued a notice for landowners eligible for compensation to apply within 21 days, providing ownership documents at the DAO, MCA Nepal’s office, or the project’s information center.
Assistant Chief District Officer Kamal Raj Bhandari stated that those dissatisfied with the notice can file a complaint with the Ministry of Home Affairs within 15 days, following the Land Acquisition Act of 1977. A recent meeting established compensation rates, with input from local representatives to ensure fair valuation.
A total of 199 towers will be constructed across Abukhaireni, Bandipur, Byas, Rishing, and Ghiring Rural Municipalities, some on government land and others on private property. The Value Determination Committee assessed land value based on various criteria, including classification and local market prices.
MCA Nepal is overseeing the construction of a 315-kilometer transmission line under the project, linking Lapsiphedi in Kathmandu to the Nepal-India border in Nawalparasi. A contract for the 400 kV New Damauli substation was signed on July 31, which will play a key role in electricity distribution to several substations.