CEO Tab
  • Home
  • Prime News
  • International Market
  • Special Report
  • Corporate
  • Opinion
  • Next Gen
  • Entertainment
No Result
View All Result
CEO Tab
  • Home
  • Prime News
  • International Market
  • Special Report
  • Corporate
  • Opinion
  • Next Gen
  • Entertainment
No Result
View All Result
CEO Tab
No Result
View All Result
Home Prime News

Compensation issue puts brake on Bardibas-Janakpur-Jayanagar railway project

CEO TAB by CEO TAB
July 3, 2019
in Prime News
0
74
SHARES
1.2k
VIEWS
Share on FacebookShare on Twitter

Gopal Prasad Baral

You might also like

Gold and Silver Prices Decline in Nepal on Monday

Oil Prices Surge After Hormuz Strait Disruption Amid Escalating Middle East Conflict

Government Temporarily Halts Mandatory Licensed Company Requirement for High-Value Property Deals

Bardibas, July 2 Implementation of the Bardibas-Janakpur-Jayanagar railway expansion project is being pushed towards uncertainty as the land-related compensation issues remain unsolved. Project’s 18-kilometer section from Bhangaha municipality-based old Bijalpura Station to Bardibas reports no progress due to disputes over the compensation issue. A 14-kilometer track has been readied from Jayanagar to Kurtha of Janakpur and the commencement of railway services here is in the final phase. Similarly, railway construction works from Kurtha of Dhanusha to old Bijalpura Station of Bhangaha municipality, Mahottari is going on, though at a snail’s pace. But the construction from the Bijalpura Station to Bardibas section has been uncertain as disputes regarding the compensation issues are yet to be settled, locals said. The whole project assisted by the Government of India is said to be completed by 2020. But, the compensation issues continued to halt further progress along the Bhangaha-Bardibas section, said Hari Prasad Dahal of Bardibas municipality. “We are gradually losing our hopes to see the railway services here,” he added. Landowners along the Bhangaha-Bardibas section have been demanding compensation on the basis of the current price. Bhishma Kumar Mahato of Bardibas-7 complained that the government has not yet issued a notice calling landowners to claim compensation for their land. Mahato said, “The Department of Railways has kept our land on hold for more than three years. Neither it calls us to take compensation, nor releases our land. It has put us in a problem.” Activities related to railway construction along this section have been obstructed after the compensation for 127 bighas of land kept on hold by the Department has not been distributed. Khadga Bahadur Singh of Bardibas-14 said, “We are ready to take compensation amount if the government called us after determining the compensation amount as per the current price.” Out of 127 bighas of land along Bardibas-Bhangaha section, kept on hold by the Department of Railways, 26 bighas are located in Mithila municipality of Dhanusha district while the remaining is in Bardibas and Bhangaha municipalities. In the meantime, the Department of Railway’s director-general Balaram Mishra has acknowledged that the construction works have been stalled due to the delay in the distribution of the compensation. According to him, the works on the Bardibas-Bhangaha section would pick up speed once the government addresses the compensation distribution issue. “The railway service would be operated on the Jayanagar-Kurtha sector within some months and construction works are in progress on the Kurtha-Bijalpura sector. Compensation for the land acquisition for the construction of the railway track from Bardibas-Bhangaha sector has still to be distributed, the construction works would be expedited once this issue is sorted out,” he said As per the Department of Railways’ schedule, construction works of the railway from Jayanagar to Kurtha would have been completed within 2018, from Kurtha to Bhangaha within 2019 and from Bijalpura of Bhangaha to Bardibas within 2020, and the railway service operated as per this plan. However, railway service has not been operated even in the first section (from Kurtha to Jayanagar) as works could not be completed as per the schedule. The work of expanding the broad-gauge railway had started in 2014. The government of India had provided Rs 7.20 billion for this project. The 51-kilometres Bijalpura (Bhangaha, Mahottari)-Janakpur (Dhanusha)- Jayanagar (India) railway service that was initiated 82 years back was damaged by a massive flood 18 years back. A key bridge at Bighi, Loharpatti in Mahottari caved in due to the flood. After suffering damage due to flood, the railway service was operated only on 29 kilometers from Janakpur to Jayanagar. The railway service on this sector too remains halted since the last six years with the initiation of upgrading works on this sector as well.

Share30Tweet19
CEO TAB

CEO TAB

Recommended For You

Gold and Silver Prices Decline in Nepal on Monday

by CEO Tab
March 9, 2026
0
NRB sells gold and silver coins for upcoming Tihar

Gold and silver prices fell in the Nepali market on Monday compared to the previous day. According to the Federation of Nepal Gold and Silver Dealers’ Association, the...

Read more

Oil Prices Surge After Hormuz Strait Disruption Amid Escalating Middle East Conflict

by CEO Tab
March 9, 2026
0
Petroleum drilling faces snag as machine snaps against hard rock

Global oil prices have surged sharply after the intensifying conflict in the Middle East caused a complete disruption in the Strait of Hormuz, one of the world’s most...

Read more

Government Temporarily Halts Mandatory Licensed Company Requirement for High-Value Property Deals

by CEO Tab
March 9, 2026
0
Real Estate Transactions in Nepal Plummet Further After Gen Z Movement

The government has temporarily suspended the rule requiring property transactions exceeding Rs 30 million to be conducted through licensed companies in metropolitan and sub-metropolitan areas. The Department of...

Read more

Nepal Sees Slight Drop in Food Imports as Government Revenue Declines

by CEO Tab
March 9, 2026
0
‘No shortage of food grains during rainy season’

Nepal recorded a modest decline in food imports during the first seven months of the current fiscal year (FY) 2025/26, according to data released by the Department of...

Read more

Gold and Silver Prices Increase Today

by CEO Tab
March 1, 2026
0
NRB sells gold and silver coins for upcoming Tihar

The price of gold and silver has increased today. The price of gold rose by NPR 5,600 per tola. According to the Federation of Nepal Gold and Silver...

Read more
Next Post

Sugarcane farmers announce agitation

Leave a Reply Cancel reply

Your email address will not be published. Required fields are marked *

Browse by Category

  • Corporate
  • Entertainment
  • Featured
  • International
  • Major Story
  • Next Gen
  • Opinion
  • Prime News
  • Special Report
  • Tete – A – Tete

EDITOR

Manish Raj Poudel
info@ceotab.com
9841317747


PUBLISHED BY

Welcome Group
www.welcomeadnepal.com

Publisher

www.ceotab.com is a premium news portal being run by Welcome Group. The website features quality business/economic news contents,  in-depth profiles of companies, stories of struggle and success of entrepreneurs, articles that assess various dimensions of  the commerce, trade and economy.

Editor

Manish Raj Poudel

info@ceotab.com

9841317747

Sub-Editor

Riza Poudel

poudelriza@gmail.com

Archives

© 2023 CEO Tab. All rights reserved.

No Result
View All Result
  • Home
  • Prime News
  • International Market
  • Special Report
  • Corporate
  • Opinion
  • Next Gen
  • Entertainment

© 2023 CEO Tab. All rights reserved.