The 132/11 kV Chobhar Substation in Kirtipur Municipality-6 has come into operation, marking a significant step towards strengthening and improving the reliability of the electricity supply system in the Kathmandu Valley.
According to the Nepal Electricity Authority (NEA), the substation is equipped with two power transformers, each with a capacity of 45 MVA. It receives electricity through the Matatirtha–Chobhar section, constructed under the Thankot–Chapagaun–Bhaktapur 132 kV double-circuit transmission line project.
Nine 11 kV feeder lines have been installed to distribute electricity to surrounding areas. Of these, three feeders supply the Pulchowk area of Lalitpur, while the remaining six serve Kirtipur and its neighbouring areas. Electricity supply to the local areas has started following the sequential energization of the feeders.
On Sunday, NEA Executive Director Dirghayu Kumar Shrestha inspected the substation and instructed officials to immediately energize the 11 kV feeders and proceed with the transfer of electrical load.
Shrestha said the substation would help manage rising electricity demand, particularly in Kirtipur and surrounding areas, as well as in Pulchowk, Lalitpur. He also stressed the importance of completing the load transfer process, noting that electricity consumption in the Kathmandu Valley increases during winter.
With the substation now operational, a portion of the electricity load currently supplied by the Syuchatar, Teku, Patan and Matatirtha substations will be transferred to Chobhar. This is expected to reduce pressure on existing substations and improve the overall reliability of electricity distribution across the valley.
The Chobhar Substation was developed as an alternative after construction of the 132 kV transmission line under the Thankot–Chapagaun–Bhaktapur project faced difficulties in the Khokana, Bungamati, Harisiddhi and Lamatar areas of Lalitpur, mainly due to land acquisition challenges and other obstacles.
Meanwhile, the construction of an approximately 4.5-kilometre 132 kV underground transmission line connecting Chobhar to Patan has been given high priority. Work is also underway to construct a 132 kV substation in Patan. Once completed, these infrastructures are expected to further strengthen the Kathmandu Valley’s electricity transmission and distribution network.
The Chobhar Substation has been built on 12 ropanis and 12 anas of land at Bhutkhel, Chobhar, owned by Himal Cement and leased for the project. A Cabinet meeting on January 31, 2022, had decided to lease the land to the NEA.
The substation was constructed under the Kathmandu Valley Power Transmission Capacity Reinforcement Project, funded through a concessional loan from the Asian Development Bank (ADB).