Kohalpur–Surkhet 132 kV Transmission Line Completed After Six-Year Delay

CEO Tab by CEO Tab
January 30, 2026
in Prime News
0
Land acquisition initiated for transmission line of Arun III
74
SHARES
1.2k
VIEWS
Share on FacebookShare on Twitter

The construction of the Kohalpur–Surkhet 132 kV transmission line has been completed after a delay of more than six and a half years, with testing scheduled to begin from Friday.

You might also like

Finance Ministry Reports Higher Budget Spending but Revenue Shortfall in Q2

Sharp Drop in Gold and Silver Prices Today

Nepal’s Commercial Banks Post 11.51% Profit Growth Despite Rising NPL Provisions

Developed under the Kohalpur–Surkhet–Dailekh 132 kV transmission line project, the line connects the Kohalpur substation in Banke with the Surkhet substation at Subbakuna. The project was jointly financed by the Government of Nepal and the Nepal Electricity Authority (NEA).

Construction began on Ashar 22, 2076 BS, with an estimated cost of Rs 650 million and an original completion timeline of two years. However, the project was completed nearly four and a half years behind schedule.

According to the NEA, electricity will be transmitted at 132 kilovolts through the double-circuit transmission line during the testing phase starting Friday. Following successful testing, the line will be brought into full commercial operation.

Once operational, the transmission line is expected to substantially improve the quality and reliability of electricity supply in Karnali Province. Industries in Surkhet, which have long struggled with low voltage and unstable power supply, are expected to benefit from improved voltage stability.

Currently, Surkhet receives electricity through a 33 kV transmission line that has been in use since 2045 BS. The limited capacity of this aging infrastructure has resulted in frequent voltage fluctuations and power tripping. Officials believe these issues will be resolved once the new 132 kV line becomes operational, paving the way for a more reliable power supply and supporting industrial growth in the region.

Share30Tweet19
CEO Tab

CEO Tab

Recommended For You

Finance Ministry Reports Higher Budget Spending but Revenue Shortfall in Q2

by CEO Tab
January 30, 2026
0
Finance_Ministry

The Ministry of Finance has made public its activities and achievements for the second quarter of the current fiscal year 2080/81 (2023/24), highlighting progress in budget execution, revenue...

Read more

Sharp Drop in Gold and Silver Prices Today

by CEO Tab
January 30, 2026
0
NRB sells gold and silver coins for upcoming Tihar

Gold and silver prices have witnessed a sharp decline today. After setting new records with daily price increases, the prices of gold and silver have fallen by the...

Read more

Nepal’s Commercial Banks Post 11.51% Profit Growth Despite Rising NPL Provisions

by CEO Tab
January 30, 2026
0
Commercial Banks Cut Interest Rates Amid Excess Liquidity

Commercial banks in Nepal recorded an 11.51 percent increase in net profits in the first half of the current fiscal year, supported by improved loan recovery, even as...

Read more

NOC Denies Cooking Gas Shortage Despite Bottlers’ Claims in Kathmandu Valley

by CEO Tab
January 29, 2026
0
PAC directs govt to restrict sale of 50 kg and 450 kg gas cylinders

Nepal Oil Corporation (NOC) has said there is no shortage in the supply of cooking gas, even as Liquefied Petroleum Gas (LPG) bottlers claim that the Kathmandu Valley...

Read more

Insurance Premiums Post Double-Digit Growth in First Half of FY

by CEO Tab
January 29, 2026
0
NIA curbs on investment of reinsurance companies

Nepali insurance companies recorded double-digit growth in premium collection during the first six months of the current fiscal year. According to records from the Nepal Insurance Authority (NIA),...

Read more
Next Post
NRB sells gold and silver coins for upcoming Tihar

Sharp Drop in Gold and Silver Prices Today

Browse by Category

  • Corporate
  • Entertainment
  • Featured
  • International
  • Major Story
  • Next Gen
  • Opinion
  • Prime News
  • Special Report
  • Tete – A – Tete

EDITOR

Manish Raj Poudel
info@ceotab.com
9841317747


PUBLISHED BY

Welcome Group
www.welcomeadnepal.com

Publisher

www.ceotab.com is a premium news portal being run by Welcome Group. The website features quality business/economic news contents,  in-depth profiles of companies, stories of struggle and success of entrepreneurs, articles that assess various dimensions of  the commerce, trade and economy.

Editor

Manish Raj Poudel

info@ceotab.com

9841317747

Sub-Editor

Riza Poudel

poudelriza@gmail.com

Archives

© 2023 CEO Tab. All rights reserved.

No Result
View All Result
  • Home
  • Prime News
  • International Market
  • Special Report
  • Corporate
  • Opinion
  • Next Gen
  • Entertainment

© 2023 CEO Tab. All rights reserved.