Narayangadh-Butwal road section sees only 46 percent progress in 5 years

CEO Tab by CEO Tab
February 8, 2024
in Prime News
0
Narayanghat-Butwal road section expansion sees sluggish progress
74
SHARES
1.2k
VIEWS
Share on FacebookShare on Twitter

The expansion of the Narayangadh-Butwal road section under the East-West Highway has been completed by only 46 percent in five years since the work began.

You might also like

Number of Registered Cooperatives in Nepal Reaches 32,325

Government Working to Resolve Tea Export Issues with India: Industry Minister

CIB Recommends Freezing Share Transactions of 56 Individuals Over Alleged Market Manipulation

The contract of the road project has already been extended twice but the work is far from over said, Information Officer of Narayangadh-Butwal Road Extension Plan, Eastern Section, Engineer Shiv Khanal. Out of the total 114 km road from Narayangadh to Butwal, 65 km road falls in the eastern section. According to Khanal, the road expansion work has not been able to accelerate due to the fact that the contractors are not working according to the plans they have made.

“We are constantly putting pressure to work according to the schedule and to complete the project on time”, he said. The China State Construction Engineering Corporation Limited was given the contract to complete the expansion project to be completed in four years, after starting the work in 2075 B.S.

Meanwhile, contract co-manager of China State Construction Engineering Corporation Limite, Rakesh Jha, said that the road expansion work cannot be completed during the second extension period and that the deadline should be extended by one more year. The road expansion woke was delayed due to various reasons including the current weather that is hampering black topping of the finish section of the road. The work of moving water supply and electricity poles as well as a 30 KV transmission lines in Siji, Gandakot and Dumkibas areas are yet to be completed, he said.

After the expansion of the existing two-lane road, the highway will be seven by seven meters on both sides. A service lane of 6 meters each will also be constructed in the market area. Information Officer Khanal said that the 42.7 km section of the road will have four lanes, while the southern section will have three lanes for about five km. In this section, 12 big bridges and 22 small bridges are under-construction. The construction of this section started with 85 per cent loan support from Asian Development Bank and the total cost of this section is 9.38 billion rupees.

Share30Tweet19
CEO Tab

CEO Tab

Recommended For You

Number of Registered Cooperatives in Nepal Reaches 32,325

by CEO Tab
May 29, 2026
0
Number of Registered Cooperatives in Nepal Reaches 32,325

According to the Economic Survey for the fiscal year 2025/26 published by the Ministry of Finance, the number of registered cooperatives across Nepal reached 32,325 by mid-March 2026....

Read more

Government Working to Resolve Tea Export Issues with India: Industry Minister

by CEO Tab
May 29, 2026
0
Government Working to Resolve Tea Export Issues with India: Industry Minister

Minister for Industry, Commerce and Supplies Gauri Kumari has stated that progress is being made toward resolving the challenges affecting Nepal’s tea exports to India. Addressing lawmakers during...

Read more

CIB Recommends Freezing Share Transactions of 56 Individuals Over Alleged Market Manipulation

by CEO Tab
May 29, 2026
0
CIB Recommends Freezing Share Transactions of 56 Individuals Over Alleged Market Manipulation

The Central Investigation Bureau (CIB) of Nepal Police has recommended freezing the share transactions of 56 prominent individuals associated with various merchant banking and insurance companies over alleged...

Read more

Federal Parliament Ready for FY 2026/27 Budget Presentation

by CEO Tab
May 29, 2026
0
Federal Parliament Ready for FY 2026/27 Budget Presentation

The Federal Parliament Secretariat has finalized all preparations for Friday’s joint parliamentary session, during which the annual revenue and expenditure estimates for the fiscal year 2026/27 will be...

Read more

DDC Pays Rs 120 Million to Dairy Farmers Amid Efforts to Clear Outstanding Dues

by CEO Tab
May 28, 2026
0
DDC Pays Rs 120 Million to Dairy Farmers Amid Efforts to Clear Outstanding Dues

The state-owned Dairy Development Corporation (DDC) has paid Rs 120 million to dairy farmers as part of its ongoing effort to clear long-pending payments. According to the DDC,...

Read more
Next Post
Parliament

HoR endorses bill on Money Laundering

Browse by Category

  • Corporate
  • Entertainment
  • Featured
  • International
  • Major Story
  • Next Gen
  • Opinion
  • Prime News
  • Special Report
  • Tete – A – Tete

EDITOR

Manish Raj Poudel
info@ceotab.com
9841317747


PUBLISHED BY

Welcome Group
www.welcomeadnepal.com

Publisher

www.ceotab.com is a premium news portal being run by Welcome Group. The website features quality business/economic news contents,  in-depth profiles of companies, stories of struggle and success of entrepreneurs, articles that assess various dimensions of  the commerce, trade and economy.

Editor

Manish Raj Poudel

info@ceotab.com

9841317747

Sub-Editor

Riza Poudel

poudelriza@gmail.com

Archives

© 2023 CEO Tab. All rights reserved.

No Result
View All Result
  • Home
  • Prime News
  • International Market
  • Special Report
  • Corporate
  • Opinion
  • Next Gen
  • Entertainment

© 2023 CEO Tab. All rights reserved.