Kathmandu view tower construction sees dismal progress; 15 percent works in five years

CEO TAB by CEO TAB
December 2, 2020
in Prime News
0
DCSCP collects Rs 4 million in fines
74
SHARES
1.2k
VIEWS
Share on FacebookShare on Twitter

-Sharmeela Pathak

You might also like

Institutional Investors Defy Market Slump, Increase Stock Market Investments

Electricity Supply to Humla Headquarters Simikot Disrupted

LPG Prices Rise by Rs 105.38 per Cylinder in Kathmandu Valley

Kathmandu, December 2 : The construction of Kathmandu view tower that began around five years back has made dismal progress of 15 percent as of now. The Kathmandu Metropolitan City (KMC) admitted that the construction progress was only 15 percent during five years since its beginning.

Former chief of KMC Public Private Partnership unit, Dhruba Kafle said that the metropolis should wait for the contracted period as per the rule despite dismal progress in construction. As per the agreement the construction progress should be almost 75 percent but the target has not been realized. The foundational works under-land have been completed while the task of installing pillar is underway now.

With this overall progress of the construction accounts 15 percent. Now daily 100 workers are being mobilized in the construction work. It may be noted that the KMC had already extended the deadline by a year to facilitate the completion of under-land construction acting on the stipulated rule. A contract was signed by the KMC and Jaleswor, Swachchhanda and BIKOI Builders around six years back for the construction of the view tower. The company however had started the construction works since 14 August 2016.

As per the agreement the construction works should be completed by 14 August 2021 but the progress does not indicate much to that end. Twenty three ropanies five ana land has been allotted for the construction of the tower. Out of this 40 percent land will be occupied by the tower structure while 60 percent will remain as open space. The high-rise tower will reflect Nepali art and culture. RSS

Share30Tweet19
CEO TAB

CEO TAB

Recommended For You

Institutional Investors Defy Market Slump, Increase Stock Market Investments

by CEO Tab
September 6, 2026
0
Institutional Investors Defy Market Slump, Increase Stock Market Investments

Institutional investors, including mutual funds and investment companies, are steadily expanding their presence in Nepal’s stock market despite a prolonged decline in share trading at the Nepal Stock...

Read more

Electricity Supply to Humla Headquarters Simikot Disrupted

by CEO Tab
September 6, 2026
0
Electricity Supply to Humla Headquarters Simikot Disrupted

Electricity supply to Simikot, the headquarters of Humla district, has been disrupted since Tuesday due to a technical problem at the Hildum Distribution Center of the Nepal Electricity...

Read more

LPG Prices Rise by Rs 105.38 per Cylinder in Kathmandu Valley

by CEO Tab
September 6, 2026
0
LPG Prices Rise by Rs 105.38 per Cylinder in Kathmandu Valley

Cooking gas bottlers have increased the price of liquefied petroleum gas (LPG) by Rs 105.38 per cylinder in the Kathmandu Valley, citing higher transportation costs after being forced...

Read more

NEPSE Declines 0.57 Percent as Investors Lose Rs 25 Billion in a Week

by CEO Tab
September 6, 2026
0
NEPSE Declines 0.57 Percent as Investors Lose Rs 25 Billion in a Week

The Nepal Stock Exchange (NEPSE) index declined by 14.54 points, or 0.57 percent, last week, although hydropower stocks recovered after suffering heavy losses in the previous week following...

Read more

Government Announces Relief Package for Entrepreneurs Affected by Bhotekoshi Floods

by CEO Tab
September 4, 2026
0
Government Announces Relief Package for Entrepreneurs Affected by Bhotekoshi Floods

The government has announced a comprehensive revival package for entrepreneurs affected by the devastating Bhotekoshi floods, offering customs duty exemptions, concessional loans, and loan restructuring facilities. The measures...

Read more
Next Post
Governors of 19 central banks agree to promote economic activities

Governors of 19 central banks agree to promote economic activities

Leave a Reply Cancel reply

Your email address will not be published. Required fields are marked *

Browse by Category

  • Corporate
  • Entertainment
  • Featured
  • International
  • Major Story
  • Next Gen
  • Opinion
  • Prime News
  • Special Report
  • Tete – A – Tete

EDITOR

Manish Raj Poudel
info@ceotab.com
9841317747


PUBLISHED BY

Welcome Group
www.welcomeadnepal.com

Publisher

www.ceotab.com is a premium news portal being run by Welcome Group. The website features quality business/economic news contents,  in-depth profiles of companies, stories of struggle and success of entrepreneurs, articles that assess various dimensions of  the commerce, trade and economy.

Editor

Manish Raj Poudel

info@ceotab.com

9841317747

Sub-Editor

Riza Poudel

poudelriza@gmail.com

Archives

© 2023 CEO Tab. All rights reserved.

No Result
View All Result
  • Home
  • Prime News
  • International Market
  • Special Report
  • Corporate
  • Opinion
  • Next Gen
  • Entertainment

© 2023 CEO Tab. All rights reserved.