Home Prime News

Sunkoshi Marine Diversion’s tunnel likely to complete in a month

CEO Tab by CEO Tab
March 31, 2024
in Prime News
0
Sunkoshi Marine Diversion’s tunnel likely to complete in a month

;'gsf];L dl/0f 8«fOe;{gdf >lds l;Gw'nLM !& r}tM l;Gw'nLdf /x]sf] ;'gsf];L dl/0f 8«fOe;{g ax'p2]ZoLo cfof]hgfsf] lgdf{0ffwLg ;'?ªleq sfd ub}{ >lds . tl:a/ M xl//fd e]6'jfn÷ /f;;

75
SHARES
1.2k
VIEWS
Share on FacebookShare on Twitter

The main tunnel of the Sunkoshi Marine Diversion is going to witness a breakthrough within a month. Of the 13.3 km tunnel of this national pride project, only 790 m is left to be completed, according to Mitra Baral, Project Chief.     

You might also like

Interest Rate Cuts and Higher Power Demand Drive Hydropower Profits to Rs 11.11 Billion

Parliamentary Panel Proposes Three-Year Tenure for NRB Top Officials

Four South Asian Countries Sign Deal to Share Advance Trade Information

The multi-billion-rupee multipurpose Project aims to provide irrigation facilities to five drought-prone districts in Madhesh province and generate 31 megawatts of electricity.     

A team comprising Minister for Energy, Water Resources and Irrigation Shakti Bahadur Basnet, Secretary at the Ministry of Energy, Water Resources and Irrigation Sushil Chandra Tiwari and Director General of Department of Hydropower and Irrigation Chandra Bahadur Oli among others made an on-site inspection of the project site at Kusumtar of Kamalamai municipality in Sindhuli district today.     

Minister Basnet, following the on-site visit, assured that there would be no resource crunch for the project to be completed on time. “This project is a special priority of the government. We make sure that there will not be any problems of resources in the project,” the Minister pledged.     

Stating that the Project had achieved satisfactory progress so far, the Minister instructed to conclude the project within the stipulated time.     

Earlier on Friday, the team also inspected the dam of the Project that is estimated to provide irrigation facility to 122,000 hectares of land in Rautahat, Dhanusha, Mahottari, Sarlahi and Bara districts.    

Project Chief Baral said that if there was no geographical complication in digging the remaining portion of the tunnel, the project would achieve a breakthrough within a month.     

The Chinese company Overseas Engineering, has been constructing the tunnel while an Indian Company Patel Engineering has partnered with Nepal’s Raman Group to build the dam of the Project. The Project is expected to be completed within mid-October 2027.     

As a part of the Project, 67 cubic metres of water per second would be diverted from the Sunkoshi River to the Bagmati River via Marin Khola of Sindhuli district.

Share30Tweet19
CEO Tab

CEO Tab

Recommended For You

Interest Rate Cuts and Higher Power Demand Drive Hydropower Profits to Rs 11.11 Billion

by CEO Tab
August 21, 2026
0
Interest Rate Cuts and Higher Power Demand Drive Hydropower Profits to Rs 11.11 Billion

Nepal’s hydropower sector recorded a sharp improvement in financial performance in the fiscal year 2025/26, with 106 hydropower companies listed on the Nepal Stock Exchange (NEPSE) reporting a...

Read more

Parliamentary Panel Proposes Three-Year Tenure for NRB Top Officials

by CEO Tab
August 21, 2026
0
Parliamentary Panel Proposes Three-Year Tenure for NRB Top Officials

The Finance Committee of the Federal Parliament has decided to amend the Nepal Rastra Bank Act, proposing to limit the regular tenure of the central bank’s top officials...

Read more

Four South Asian Countries Sign Deal to Share Advance Trade Information

by CEO Tab
August 21, 2026
0
Four South Asian Countries Sign Deal to Share Advance Trade Information

Nepal, Bhutan, Bangladesh and the Maldives have signed an agreement to exchange advance information on goods traded across their borders, in a move aimed at facilitating regional trade...

Read more

Government Moves to Introduce Seasonal Electricity Tariffs

by CEO Tab
August 21, 2026
0
Government Moves to Introduce Seasonal Electricity Tariffs

The government has intensified preparations to reduce electricity tariffs through a proposed ‘seasonal tariff’ system, under which electricity prices would be lowered during the rainy season when surplus...

Read more

Government Sets Two-to-Five-Year Deadline to Complete Six National Pride Irrigation Projects

by CEO Tab
August 19, 2026
0
Government Sets Two-to-Five-Year Deadline to Complete Six National Pride Irrigation Projects

The government has set ambitious deadlines to complete six long-delayed national pride irrigation projects, with completion targeted within the next two to five years. The Ministry of Energy,...

Read more
Next Post
Finance_Ministry

Federal govt approves Rs 300 billion for provincial and local govts

Browse by Category

  • Corporate
  • Entertainment
  • Featured
  • International
  • Major Story
  • Next Gen
  • Opinion
  • Prime News
  • Special Report
  • Tete – A – Tete

EDITOR

Manish Raj Poudel
info@ceotab.com
9841317747


PUBLISHED BY

Welcome Group
www.welcomeadnepal.com

Publisher

www.ceotab.com is a premium news portal being run by Welcome Group. The website features quality business/economic news contents,  in-depth profiles of companies, stories of struggle and success of entrepreneurs, articles that assess various dimensions of  the commerce, trade and economy.

Editor

Manish Raj Poudel

info@ceotab.com

9841317747

Sub-Editor

Riza Poudel

poudelriza@gmail.com

Archives

© 2023 CEO Tab. All rights reserved.

No Result
View All Result
  • Home
  • Prime News
  • International Market
  • Special Report
  • Corporate
  • Opinion
  • Next Gen
  • Entertainment

© 2023 CEO Tab. All rights reserved.