CEO Tab
  • Home
  • Prime News
  • International Market
  • Special Report
  • Corporate
  • Opinion
  • Next Gen
  • Entertainment
No Result
View All Result
CEO Tab
  • Home
  • Prime News
  • International Market
  • Special Report
  • Corporate
  • Opinion
  • Next Gen
  • Entertainment
No Result
View All Result
CEO Tab
No Result
View All Result
Home Prime News

NEA concern in construction progress of transmission line

CEO Tab by CEO Tab
April 27, 2022
in Prime News
0
Nepal Electricity Regulatory Commission (NERC)
74
SHARES
1.2k
VIEWS
Share on FacebookShare on Twitter

The Nepal Electricity Authority (NEA) has expressed concern over the progress of the Marsyangdi Corridor transmission line after receiving complaints that the completed projects could not be connected to the central transmission system.

You might also like

Nepal’s Trade Costs 44% Higher Than SAFTA Average: Govt Report

APF Tightens Border Monitoring to Curb Revenue Leakage

FDI Commitments Near Rs 41.79 Billion in Nine Months

A team including NEA executive director has inspected the transmission line and substation and got information about the latest situation.

Construction of four substations under the Marsyangdi Corridor Transmission Line Project with a total capacity of 220 KV is in full swing. Under the project, 220 KV substations are being constructed in New Bharatpur of Chitwan, Udipur of Lamjung and Khudi and Dharapani of Manang.

According to NEA, work is underway to complete the construction of new Bharatpur and Udipur substations within three months. Similarly, construction of Khudi substation is targeted to be completed within a year while construction of Dharapani substation has started. Due to its geographically remote location, the construction of Dharapani substation will take some time.

The new Bharatpur and Udipur substations will have power transformers of 220/132 KV, 320 MVA and 220/132 KV, 160 MVA and 132/33 KV, 50 MVA capacity respectively. The construction of the main civil structure of both the substations has reached the final stage and the equipment is being connected.


Khudi and Dharapani substations will have 220/132 KV, 160 MVA and 132/33 KV, 50 MVA and 220/132 KV, 100 MVA and 132 ÷ 33 KV, 30 MVA capacity power transformers respectively. The main civil structures of Khudi substation are under construction. A high management team led by NEA Executive Director Kulman Ghising has carried out detailed discussions with the project management, consultants and construction businessmen about the progress being made in the construction of the substation, problems seen at the project site and work completion schedule.

Executive Director Ghising urged to complete the transmission line and substation on time as it is important for the flow of electricity of the private sector hydropower project under construction in Marsyangdi Corridor. He directed the project management to expedite the approval process for forest use and tree felling in the forest area and to start construction of transmission line by resolving social issues.

He said that he was ready to take necessary initiatives and coordination at the upper level for this. The Dordi corridor of the hydropower project under construction on Dordi river in Lamjung will be connected to Udipur substation through transmission line.

As the construction of Udipur substation will take some time, the electricity of Dordi Khola project will be connected to the switchyard of Madhyamrsyangdi power house which is currently in operation through alternative arrangement.

The power will be connected to the substation of the hydropower project under construction at Ngadi and its tributaries in Lamjung. The Marsyangdi Corridor 220 KV transmission line project has been started for the flow of electricity generated in Marsyangdi and its tributaries to the national transmission system.

About 1,600 MW of electricity will be able to flow from the transmission line.

The length of double circuit transmission line from Bharatpur of Chitwan to Dharapani of Manang is about 113 kilometers. The project is being divided into three packages.

Under the first package, about 67 kilometers of transmission line is being constructed from Udipur to the new Bharatpur substation. New Bharatpur and Udipur substations are under construction under the second package.

Under the third package, 46 km transmission line and two substations are being constructed from Khudi to Dharapani. The estimated cost of the project under construction is about Rs. 16 billion with the investment of Government of Nepal and concessional loan from European Investment Bank (EIB).

Share30Tweet19
CEO Tab

CEO Tab

Recommended For You

Nepal’s Trade Costs 44% Higher Than SAFTA Average: Govt Report

by CEO Tab
April 16, 2026
0
“Issues of price increment of petroleum goods will be resolved”

Nepal’s trading cost is 44 percent higher than those of member countries of the South Asian Free Trade Area (SAFTA), according to a new government report highlighting deep-rooted...

Read more

APF Tightens Border Monitoring to Curb Revenue Leakage

by CEO Tab
April 16, 2026
0
Exports of Nepali goods double in four months

The Armed Police Force (APF) Nepal has intensified monitoring at eastern border customs points, including Kakarbhitta, in a bid to control revenue leakage. The move follows growing concerns...

Read more

FDI Commitments Near Rs 41.79 Billion in Nine Months

by CEO Tab
April 16, 2026
0
FDI commitment declined 60% during five months

Foreign Direct Investment (FDI) commitments in Nepal have reached nearly Rs 41.79 billion in the first nine months of the current fiscal year, according to the Department of...

Read more

Nationwide Economic Survey Begins, 5,000 Personnel Deployed

by CEO Tab
April 15, 2026
0
Nepal’s Second Economic Census to Begin on March 15

The second nationwide economic survey has commenced today, with the National Statistics Office (NSO) confirming that enumerators and supervisors have already been deployed to their assigned areas. The...

Read more

Govt Unveils Ambitious Plan for 7% Growth and $100 Billion Economy

by CEO Tab
April 15, 2026
0
OPMCM

The government has pledged to achieve an average economic growth rate of 7 percent over the next five years, with targets to raise per capita income to $3,000...

Read more
Next Post
"We are not in position to pay loans"

Banks increase base rates; higher interest rates on loans

Browse by Category

  • Corporate
  • Entertainment
  • Featured
  • International
  • Major Story
  • Next Gen
  • Opinion
  • Prime News
  • Special Report
  • Tete – A – Tete

EDITOR

Manish Raj Poudel
info@ceotab.com
9841317747


PUBLISHED BY

Welcome Group
www.welcomeadnepal.com

Publisher

www.ceotab.com is a premium news portal being run by Welcome Group. The website features quality business/economic news contents,  in-depth profiles of companies, stories of struggle and success of entrepreneurs, articles that assess various dimensions of  the commerce, trade and economy.

Editor

Manish Raj Poudel

info@ceotab.com

9841317747

Sub-Editor

Riza Poudel

poudelriza@gmail.com

Archives

© 2023 CEO Tab. All rights reserved.

No Result
View All Result
  • Home
  • Prime News
  • International Market
  • Special Report
  • Corporate
  • Opinion
  • Next Gen
  • Entertainment

© 2023 CEO Tab. All rights reserved.