Work plan for restoring Melamchi water supply by mid-April

CEO Tab by CEO Tab
January 31, 2022
in Prime News
0
Tunnel works in Melamchi Water Supply Project near-final phase
74
SHARES
1.2k
VIEWS
Share on FacebookShare on Twitter

Minister for Water Supply and Sanitation Umakanta Chaudhary has said a work plan has been prepared and works are being carried out accordingly for re-directing water from Melamchi to Kathmandu by mid-April this year.

You might also like

Nepal Oil Corporation Keeps Existing Fuel Prices Unchanged

Nepal Government’s Capital Expenditure Stuck at 32.53% With One Month Left in Fiscal Year

BFIs’ Margin Lending Against Shares Rises 15.5% to Rs 162.53 Billion

Addressing a press conference at the Ministry, he said the Chinese construction company, Sino Hydro, is carrying out works as per its commitment to completing its responsibility within three months from the date of starting the works.

“Works are being carried out 24 hours for removing the debris deposited by the massive flooding in the in-take area of the project preparing daily work plan using 12 excavators and 24 tippers. Arrangements have been made for making an assessment of the works every seven days,” the Water Supply Minister said.

He gave assurances that 1.7 million liters of water which is the previous amount of water supplied from the Melamchi stream to Kathmandu Valley would be restored even on a temporary basis.

Minister Chaudhary said the permanent structures of the project would be restored on the basis of the study report prepared by the Asian Development bank.

Stating that works related to the dam and tunnel of the project are being carried out presently on a war footing, he said a flood warning signal system would be installed at the dam site for minimizing the damage during the monsoon season.

Flood triggered by incessant rainfall on June 15, 2021 had caused massive damage to the dam and tunnel of the Melamchi Water Supply project site in Sindhupalchok district.

Share30Tweet19
CEO Tab

CEO Tab

Recommended For You

Nepal Oil Corporation Keeps Existing Fuel Prices Unchanged

by CEO Tab
June 16, 2026
0
Nepal Oil Corporation Keeps Existing Fuel Prices Unchanged

The Nepal Oil Corporation (NOC) has decided to continue the existing retail prices of petroleum products without any change. Although the corporation has received revised purchase prices from...

Read more

Nepal Government’s Capital Expenditure Stuck at 32.53% With One Month Left in Fiscal Year

by CEO Tab
June 16, 2026
0
Nepal Government’s Capital Expenditure Stuck at 32.53% With One Month Left in Fiscal Year

The government has spent only 32.53 percent of its allocated development budget, raising concerns over weak capital expenditure performance with just one month remaining in the current fiscal...

Read more

BFIs’ Margin Lending Against Shares Rises 15.5% to Rs 162.53 Billion

by CEO Tab
June 16, 2026
0
BFIs’ Margin Lending Against Shares Rises 15.5% to Rs 162.53 Billion

Banks and financial institutions (BFIs) in Nepal have increased their lending against share collateral by 15.5 percent, reaching a total of Rs 162.53 billion over the first 10...

Read more

NRB Flags Weak Governance, Rising Bad Loans and Regulatory Evasion in Banking Sector

by CEO Tab
June 16, 2026
0
NRB Flags Weak Governance, Rising Bad Loans and Regulatory Evasion in Banking Sector

Nepal Rastra Bank (NRB) has identified serious structural and governance-related problems in banks and financial institutions (BFIs), warning that weak oversight, rising non-performing loans, and regulatory evasion practices...

Read more

Nagdhunga–Sisnekhola Tunnel Set to Open in Mid-July as Final Preparations Near Completion

by CEO Tab
June 15, 2026
0
Nagdhunga–Sisnekhola Tunnel Set to Open in Mid-July as Final Preparations Near Completion

Nepal’s first commercial highway tunnel, the Nagdhunga–Sisnekhola Tunnel Road, is expected to come into operation from mid-July with final technical and operational preparations currently underway. According to project...

Read more
Next Post
Finance-Minister

Finance Minister admits lack of development-friendly policy

Browse by Category

  • Corporate
  • Entertainment
  • Featured
  • International
  • Major Story
  • Next Gen
  • Opinion
  • Prime News
  • Special Report
  • Tete – A – Tete

EDITOR

Manish Raj Poudel
info@ceotab.com
9841317747


PUBLISHED BY

Welcome Group
www.welcomeadnepal.com

Publisher

www.ceotab.com is a premium news portal being run by Welcome Group. The website features quality business/economic news contents,  in-depth profiles of companies, stories of struggle and success of entrepreneurs, articles that assess various dimensions of  the commerce, trade and economy.

Editor

Manish Raj Poudel

info@ceotab.com

9841317747

Sub-Editor

Riza Poudel

poudelriza@gmail.com

Archives

© 2023 CEO Tab. All rights reserved.

No Result
View All Result
  • Home
  • Prime News
  • International Market
  • Special Report
  • Corporate
  • Opinion
  • Next Gen
  • Entertainment

© 2023 CEO Tab. All rights reserved.