CEO Tab
  • Home
  • Prime News
  • International Market
  • Special Report
  • Corporate
  • Opinion
  • Next Gen
  • Entertainment
No Result
View All Result
CEO Tab
  • Home
  • Prime News
  • International Market
  • Special Report
  • Corporate
  • Opinion
  • Next Gen
  • Entertainment
No Result
View All Result
CEO Tab
No Result
View All Result
Home Prime News

Only 74% of Butwal–Narayanghat Highway Upgrade Completed in Six Years, New Deadline Set for 2026

CEO Tab by CEO Tab
November 18, 2025
in Prime News
0
Narayangadh-Butwal road reports 50 percent progress in over five years
75
SHARES
1.2k
VIEWS
Share on FacebookShare on Twitter

Six years after the upgrade work began, only 74 percent of the Butwal–Narayanghat section of the East–West Highway has been completed, confirming that the project will not be finished this year as previously expected. Officials at the Ministry of Physical Infrastructure and Transport (MoPIT) say they remain hopeful that the remaining work can be completed next year.

You might also like

NEPSE Falls Nearly 50 Points Amid Investigation Concerns

Construction Begins on Myagdi Corridor Transmission Line Project

Majority of Kathmandu Cooperatives Fail to Meet Reporting and Renewal Deadlines

Joint Secretary Chudaram Dhakal, head of the ADB Project Directorate at the ministry, said progress on the most difficult Daunne section has reached only around 50 percent, making it a primary bottleneck in project completion.

In July, the Department of Roads (DoR) extended the project deadline for the fourth time, setting July 21, 2026, as the final deadline for the western segment and July 23, 2026, for the eastern segment. Dhakal expressed confidence that the extended timeframe will be met.

“This is the final deadline. The work must be completed within it. After 70 percent progress, contractors generally do not back away,” he said.


Daunne Stretch Remains the Biggest Challenge

The road is divided into two segments, with the expired deadlines falling in mid-July. Although only 14 km long, the Daunne stretch is known as the most chaotic part of the corridor, where vehicles often take one to two hours to pass through. Its length is split into 4 km in the eastern section and 10 km in the western section.

The contractor agreed to the deadline extension on the condition of no additional financial claims or compensation. A senior ministry official said terminating the contract would have complicated the project even further:

“Replacing the contractor would cause bigger delays, so extending the contract was the only feasible option.”

The contractor has argued that work remained stalled for almost three years due to COVID-19. The project, awarded to China State Construction Engineering for Rs 17.02 billion, was initially signed on December 19, 2018. After missing the third extended deadline of July 23, 2025, the fourth extension was approved.


Project Composition and Delays

The 113-km highway stretch includes:

  • 64.425 km (Eastern Segment)
  • 48.535 km (Western Segment)

The project is being executed by the ADB Directorate under the DoR with financial support from the Asian Development Bank.

A senior DoR official admitted that delays were caused by both the contractor and internal shortcomings:

  • Delayed site clearance
  • Difficulties obtaining tree-cutting permits
  • Slow relocation of electricity poles
  • Limited access to construction materials due to local extraction restrictions

“The DoR should have coordinated better with contractors and local governments,” the official acknowledged.


Night-Time Construction in Gaindakot

To reduce daytime congestion, road expansion work in Gaindakot is now being carried out from 10 p.m. to 4 a.m. every day. Around 170 meters west of the Narayani bridge still remains to be blacktopped.

Except for Gaindakot and the Daunne hill portion, one-way blacktopping on the eastern segment has been completed.

Under the expansion design:

  • 100 km of the highway will be upgraded to four lanes
  • The 14-km Daunne section will be limited to three lanes due to terrain constraints
  • Two additional service lanes will be added on both sides in urban stretches
Share30Tweet19
CEO Tab

CEO Tab

Recommended For You

NEPSE Falls Nearly 50 Points Amid Investigation Concerns

by CEO Tab
May 3, 2026
0
10 firms keen to receive stockbrokers licenses

The Nepal Stock Exchange (NEPSE) dropped by 49.98 points, or 1.79 percent, over the past week, as government investigations into several high-profile individuals accused of misusing public funds...

Read more

Construction Begins on Myagdi Corridor Transmission Line Project

by CEO Tab
May 3, 2026
0
Land acquisition initiated for transmission line of Arun III

Construction has started on a 132-KV transmission line under the Myagdi Corridor, aimed at supporting multiple hydropower projects along the Myagdi River. The project involves building double and...

Read more

Majority of Kathmandu Cooperatives Fail to Meet Reporting and Renewal Deadlines

by CEO Tab
May 3, 2026
0
DoC sets guidelines for cooperatives seeking merger 

Nearly two-thirds of cooperatives operating in Kathmandu district have neither submitted their annual financial reports nor renewed their licenses on time, according to authorities. Data from the Department...

Read more

Truck Gridlock at Nepal Customs After MRP Rule Sparks Trader Protest

by CEO Tab
May 3, 2026
0
Mandatory MRP Labelling and Billing Rule Enforced for Imported Goods

Customs points across Nepal have been overwhelmed by long queues of trucks carrying imported goods after traders refused to clear shipments in protest against the government’s mandatory maximum...

Read more

Nepal’s Economy Projected to Reach Rs 6.6 Trillion, but Growth Slows to 3.85%

by CEO Tab
April 29, 2026
0
Nepal’s Second Economic Census to Begin on March 15

Nepal’s economy is projected to reach Rs 6.6 trillion by the end of the current fiscal year (FY), marking an increase of Rs 401 billion, according to preliminary...

Read more
Next Post
Finance_Ministry

Government Fails to Meet Revenue Target in First Four Months of FY 2025/26

Browse by Category

  • Corporate
  • Entertainment
  • Featured
  • International
  • Major Story
  • Next Gen
  • Opinion
  • Prime News
  • Special Report
  • Tete – A – Tete

EDITOR

Manish Raj Poudel
info@ceotab.com
9841317747


PUBLISHED BY

Welcome Group
www.welcomeadnepal.com

Publisher

www.ceotab.com is a premium news portal being run by Welcome Group. The website features quality business/economic news contents,  in-depth profiles of companies, stories of struggle and success of entrepreneurs, articles that assess various dimensions of  the commerce, trade and economy.

Editor

Manish Raj Poudel

info@ceotab.com

9841317747

Sub-Editor

Riza Poudel

poudelriza@gmail.com

Archives

© 2023 CEO Tab. All rights reserved.

No Result
View All Result
  • Home
  • Prime News
  • International Market
  • Special Report
  • Corporate
  • Opinion
  • Next Gen
  • Entertainment

© 2023 CEO Tab. All rights reserved.